The February 27, 2004 demonstration follows up
on presentations given at the Engineering Model 2 Review,
at which the FSW team presents designs
for several major software functions.
Demonstration Agenda
-
TKR and CAL Demos
-
LCB Package Test Demo
-
Watchdog Function Demo
(NOTE: The Watchdog demo is rescheduled for March 2004)
Goals of the Demonstrations
The demonstrations have the following goals:
-
The TKR and CAL Demonstrations show
that the DEM software package,
used to configure and capture event data
from these LAT subsystems,
is complete and operational.
The software successfully writes and reads registers
on a Tower Electronics Module (TEM).
It can also be used to instruct the TEM
to turn off selected TKR and CAL contributions
to event data sets.
-
The LCB Package Test Demonstration
shows that the LCB software package
runs on a CPU crate and interrogates the PCI hardware
of a LAT Communications Board in that crate.
This demo also shows that test scripts for the LCB package
have been written and execute successfully
on the LAT Flight Software Test Executive (LTX) system.
-
The Watchdog Function Demonstration shows
that a proof-of-concept design for the software Watchdog
is complete,
and a test implementation of this design
runs on a RAD750 processor.
|