| Documentation to Complete for CDR |
Responsible Subsystem |
Document Number |
Completion
Date |
STATUS |
|---|---|---|---|---|
| CDR Presentation | ||||
|
ACD CDR Presentation Package (for LAT CDR) |
Manager, All | N/A | 15-Mar-03 |
DRAFT PDF | PowerPoint |
| Requirements & Interface Definitions | ||||
| Level III Requirements | Systems | LAT-SS-00016 | 24-Aug-03 | Complete |
| Level IV Requirements | Systems | LAT-SS-00352 | 20-Dec-02 | Controlled (In Signoff) |
|
ACD-LAT ICD, Rev 5 (Mech, Therm & Elect) |
Systems | LAT-SS-00363 | 30-Aug-02 | Complete |
| Electrical Specification | Electrical | ACD-PROC-000051 | 02-Jan-03 | Draft |
| System Performance and Analysis | ||||
| Mass and Power Updates | Systems, Mech, Elect | N/A | 30-Dec-02 | Mass | Power |
| Thermal | Thermal | 02-Jan-03 | Draft | |
| Structural | Mechanical | 02-Jan-03 | Draft (In Progress) | |
| Electrical/Electronics | ||||
| GAFE2 Test Report | Electrical | ACD-RPT-000074 | 24-Oct-02 | Compete |
| GARC Version 1 Test Report | Electrical | ACD-RPT-000073 | 27-Sep-02 | Compete |
| Micrometeoroid Shield Analysis | Johnson | LAT-TD-01122-1 | 06-Nov-02 | Complete |
| Eng Model Test Reports | ||||
| Thermal Vacuum Test Results | Thermal | 03-Jan-03 | Draft | |
| Vibration Tile Performance | Mech, Elect, Therm | ACD-RPT-000070 | 04-Nov-02 | Complete |
| EMI/EMC | Systems | 02-Jan-03 | ||
| Science Performance | ||||
| Light Collection/Optical | Science | LAT-TD-00438-D3 | 26-Dec-02 | Draft |
| Supplemental Detector | Science | LAT-TD-01239-D1 | 26-Dec-02 | Draft |
| Manufacturing, Test, and Verification Plans | ||||
|
ACD TDA Fabrication and Assembly Procedure |
ACD-PROC-000059 | 16-Oct-02 | Draft | |
| I&T Test Plan | I&T | LAT-TD-00430-D1 | 02-Jan-03 | Draft |
|
Functional Test Plans (Comprehensive Performance Test) |
I&T | LAT-TD-01112-D1 | 02-Jan-03 | Draft |
| Subassemblies Test Plans | ||||
|
Tile Detector Assembly Quality Plan and Acceptance Tests |
Electrical | LAT-TD-01203-D1 | 13-Dec-02 | Draft (In Signoff) |
|
Photomultiplier Tube Quality Plan and Acceptance Tests |
Electrical | LAT-TD-01202-D1 | 18-Sep-02 | Draft (In Signoff) |
| FREE Test Plan | Electrical | ACD-PROC-000051 | 16-Dec-02 | Draft |
| PMT Test Plan | Electrical | ACD-PROC-000066 | 30-Dec-02 | Draft |
| GAFE Test Plan | Electrical | ACD-PROC-000067 | 10-Jan-03 | Draft |
| GARC Test Plan | Electrical | ACD-PROC-000062 | 15-Aug-02 | Draft |
| Verification Plan | Systems | ACD-PLAN-000050-D5 | 02-Jan-03 | Draft (In Signoff) |
| Structural Design and Test Loads | Systems | ACD-SPEC-3006 | 18-Dec-02 | Draft |
|
Performance Monitoring and In-Flight Calibration |
LAT-TD-01206-D1 | 20-Dec-02 | Draft | |
| System & Mission Assurance | ||||
| Risk Management | ||||
| Risk List/Assessments | Systems, Reliability | 02-Jan-03 | Draft | |
| Fault Tree Analysis | Systems, Reliability | ACD-RPT-000072 | 02-Jan-03 | Draft |
| Quality Control Plan | QA | LAT-MD-846.1 | 24-Aug-01 | Complete |
| Configuration Management Plan | CM | LAT-MD-845.1 | 04-Jan-02 | Complete |
| FMEA Report/Critical Items List | Reliability | LAT-TD-00913-01 | 25-Oct-01 | Complete |
| Limited Life List | Reliability | LAT-TD-01123-01 | 21-Oct-02 | Complete |
|
Reliability Analysis/ Worst Case Analysis |
Reliability | ACD-RPT-000071 | 13-Sep-02 | Draft |
| Support Materials | ||||
|
Mechanical Materials, Parts, and Processes |
Mechanical, Parts | LAT-DS-00405-3 | 02-Jan-03 | Draft |
| Elect Parts List | Electrical, Parts | 23-Dec-02 |
Complete (Regular Updates) |
|
| Transportation and Handling Plan | Mechanical | 02-Jan-03 | TBD | |
| Drawings (LAT also calls this Level V, incl GSE) | ||||
| Subsystem Drawing Tree | Mechanical | 02-Jan-03 | Draft | |
| Part 1 | Mechanical | GE2054502-11 | 02-Jan-03 | Draft |
| Part 2 | Mechanical | GE2054502-21 | 02-Jan-03 | Draft |
| Project Management - Planning | ||||
| Schedule | Management | 11-Oct-02 |
Complete (Continual Updates) |
|
| Cost | Management | 11-Oct-02 |
Complete (Continual Updates) |
|